Managing a project comes down to three things: knowing what has to be done, who does it and by when — and reviewing it every week. This page explains the method and how each part of the hub supports it.
</aside>
The three areas you manage
| Area |
Question it answers |
Where it lives |
Healthy signal |
| Tasks & priorities |
What needs doing, and what comes first? |
Tasks → Board |
Max. 3 tasks “In progress” per person; nothing overdue without a plan |
| Time |
When does each thing happen — will we hit the date? |
Tasks → Timeline, Weekly Planner, Dashboard |
% of tasks done keeps pace with % of time elapsed |
| Team |
Who does what, and how do we coordinate? |
Team, Phases (RACI), Communication Plan |
Every task has one owner; every message has one channel |
Money sits alongside all three in Budget. And one principle over everything: control the basics — dates, money, owners — and leave room for the creative work. Over-controlling is its own risk.
The method in 8 steps
Do steps 1–5 once at the start. Steps 6–8 repeat every week until you close.
- Define the project — Brief. Write a SMART objective (specific, measurable, achievable, relevant, time-bound). State clearly what is in scope and what is not: that line protects you from scope creep.
- Split it into phases — Phases. Four to eight phases, each closed by a milestone you can verify (“Website approved”, not “work on website”).
- Anticipate risks — Risks. List three or four things that could go wrong, with probability, impact and your plan. The Score (1–9) sorts them automatically.
- Assign responsibilities — Team + Phases. Add everyone, even if it is just you and a few vendors. In each phase, mark who does the work (R), who approves (A — one person only), who is consulted (C) and who is informed (I).
- List the tasks — Tasks. Concrete verbs, one owner each, a phase, a priority, start and due dates. Rule of thumb: if a task takes more than two weeks, split it. Use Blocked by for dependencies.
- Visualize the plan — Board, Timeline, Calendar. They fill themselves from Tasks. If the timeline shows too many bars in the same week, move dates.
- Track the money — Budget. Log each cost when you commit to it. Keep ~10% as contingency. Anything more than 10% over plan is flagged automatically.
- Review, communicate, adjust — Weekly Review + Dashboard. Update statuses, check what is overdue, pick the week’s three priorities and send a short status update. When the project ends, fill in the Retrospective.
Your weekly rhythm
| When |
Time |
What you do |
| Every morning |
10 min |
Open the Board, choose 1–3 tasks for today, handle messages in your fixed block |
| Once a week (same day) |
30 min |
Run the Weekly Review checklist and send the status update |
| At each milestone |
45 min |
Compare plan vs. actual (dates and money), refresh risks, get approvals in writing |