Milestones

Milestone Term Target date Status
1 Project scoping and design (FYP-1): architecture decisions, communication protocol, sandbox design, dashboard model, form alignment, supervisor confirmation on evaluation scope Term 1 Completed 27/09/2026 Done
2 Core system implementation (FYP-2): data models and ticket FSM, config and loader, orchestrator loop, sandbox controller, Docker access Term 1 Completed 25/09/2026 Done
3 Dashboard and UI (FYP-3): chat feed and kanban board, custom roles editor, intervention controls Term 1 Completed 25/09/2026 Done
4 Evaluation harness (FYP-4): task and scoring models, hidden test isolation, MAST failure tagger, single-agent baseline, runner and CLI Term 1 Completed 25/09/2026 Done
5 Real Claude-backed agent across every ticket stage, and the first real end-to-end pipeline run on the live API Term 1 Completed 28/09/2026 Done
6 Option B: hierarchical-versus-flat comparison runner and LLM rubric judge, run live against real tasks Term 1 Completed 29/09/2026 Done
7 Human-eval study delivery mechanism (FYP-36) Term 1 Completed 29/09/2026 Done
8 Dashboard visual redesign and interactive kanban (FYP-34, FYP-35) Term 1 Built 29/09/2026 Done, pushed to its own branch, not yet merged to master
9 Top-down 3D office visualization: static shell (FYP-37), agent characters at their home stations (FYP-38), navigation with the walk cycle (FYP-39), the behaviour model with its ticket failure paths (FYP-40), the scenario library with playback controls (FYP-41) and observation with the event log (FYP-42) all done. Only the live orchestrator event stream (FYP-43) remains, and it was deliberately deferred Term 1 Layers 1 to 6 done 30/09/2026 and 01/10/2026; Layer 7 deferred Built, Layers 1-6 of 7; Layer 7 deferred by design
10 Project poster (FYP-45 to FYP-48 done): example posters studied, content chosen, built as a page, diagrams and screenshots prepared, symmetry measured, exported as a PDF. The human evaluation study has a reserved space. Ethics approval, the poster's requirements and the final pre-print checks are open (FYP-49 to FYP-52) Term 1 Draft done 05/10/2026 Draft built; not for printing or submission yet
11 First supervisor meeting with Ziyang Term 1 08/10/2026, 3:30pm to 4pm Scheduled
12 Documentation and report (FYP-5): the dissertation itself, chapter by chapter Term 1 TBC Not started

Target dates marked TBC are genuinely not set yet. I will fill them in once I have real deadlines from the module handbook or from Ziyang, rather than guess at them here.