Version: 0.3 · 15 September 2026
Deck: 39 slides
A4 — Sprint 1 Demo & Presentation
| Slides | Section | Content |
|---|---|---|
| 1 – 2 | Opening | Title and contents |
| 3 – 4 | Sprint 1 overview | Team and roles |
| 5 – 6 | Main idea | Public academic website, private admin panel and Calendly booking |
| 7 – 8 | Demo | Staging build; public site and admin walkthrough |
| 9 – 10 | Committed vs delivered | Completed scope, carried-over release and deferred production deployment |
| 11 – 14 | Risks and readiness | Assumptions, revisit triggers and security checks |
| 15 – 24 | Technical appendix | Requirements, wireframes, navigation, architecture, API, authentication, data and backend |
| 25 – 27 | Sprint | Review cycle and Sprint 1 goal |
| 28 – 34 | DevOps | Environments, pipeline, configuration, design and release loop, research output |
| 35 – 36 | Documentation | Notion project portal and documentation categories |
| 37 – 39 | Sprint 2 and close | Proposed goals, dependencies and thanks |
| Item | Status | Note |
|---|---|---|
| Events module | Done | Create, edit, participants and media |
| Public content pages | Done | About, Research, Publications, Teaching and Team |
| Calendly booking | Done | Includes a Turnstile check |
| Public release to production | Carried over | Released in Sprint 2 |
| Production deployment (Vercel) | Moved to Sprint 2 | Staging only in Sprint 1 |
Release the deferred features with stakeholder sign-off, establish production on Vercel independently from staging, and close the open items in the DevOps guide.