Sprint 2 Retrospective

Review of how the team worked in Sprint 2 and what to improve in the next sprint.

</aside>

Went well Did not go well Improvement
Every merge ran lint, type checks and the full test suite (619 tests) before staging was released Only 1 of 27 pull requests (#29) carries a recorded review One teammate's review before every merge
Production went live and stays inside free plans Most commits came from one member (109 of 138) Share features across the team, one owner each
Every significant decision was written up as an ADR (ADR-016 to ADR-024) Staging and production share one database Give production its own database
The customer's design direction was adopted early and recorded (ADR-018) A sign-in problem was found only in production (5 October) Test sign-in end to end on staging before each release
Scope changes were confirmed with the customer before building Nothing measures uptime Add a free uptime monitor for both addresses