π GEM Resource Hub Β· π Library Β· π About RocketLevel Β· π Playbooks Β· πΊοΈ What's Your Market Worth? Β· π Book a Call
A resource from RocketLevel for restoration company owners and finance leads, backed by decades of experience in the trade. About a 7-minute read.
There's one operational number that touches almost everything, and it rarely gets written down: cycle time, how long a job takes to move from the first call to completed to paid. It feels like a back-office metric, but it's one of the biggest levers an owner controls. A shorter cycle means cash comes back faster and crews and equipment free up sooner to take the next job. A longer cycle ties up both.
Cycle time is the elapsed days across a job's life. Two cuts of it matter most. Production cycle time runs from the first call to job complete, and it tells you how fast you deliver and free up crews and equipment. Cash cycle time runs from the first call to payment collected, and it tells you how long your money is tied up in each job. Watch both. A shop can be fast in the field and still bleed cash if the gap between completion and payment is long.
Numbers make it concrete. In the ten-job example below, the 37 days between complete and paid is money you are lending out at zero percent. If those ten jobs averaged $18,000, that is $180,000 sitting in someone else's hands for 37 days. Pull the gap down to 20 days and you release roughly $83,000 of it back into the business ($180,000 x 17 / 37) without selling one new job.
| Measure (ten-job example) | Runs from | Average |
|---|---|---|
| Production cycle | First call to job complete | 34 days |
| Cash cycle | First call to payment collected | 71 days |
| The gap | Job complete to paid | 37 days, with $180,000 in someone else's hands |
If your crews and equipment free up a week sooner per job, you can run more jobs through the same shop without adding a single resource, which is real capacity created for free. And if cash comes back a week sooner, you're financing less work in progress and easing the exact cash gap that strains growing restoration companies.
In our experience, long cycles usually come from the waiting between steps, not the drying itself. The job that sits after mitigation before the rebuild is scheduled. The estimate that takes a week to write. The completed job that waits ten days to be invoiced. Map your typical job stage by stage with rough days at each, and the long bars turn out to be handoffs rather than work. Those are the same gaps a production board surfaces, and they are where the cycle gets shortened.
The two totals tell you the cycle is long. Splitting it into legs shows where. Put five dates on every job and the whole life of it breaks into four legs, each with a different person who can move it.
| Leg | Runs from, to | Who usually owns it | What usually stalls it | Ten-job example |
|---|---|---|---|---|
| 1. Response | First call to crew on site or job started | Dispatch and the office | After-hours coverage, a missed callback, waiting on a signed work authorization | 3 days |
| 2. Production | Job started to job complete | Project manager and crew lead | The gap between mitigation and rebuild, estimate approvals, material lead times | 31 days |
| 3. Closeout | Job complete to final invoice sent | Project manager, then the office | An unsigned Certificate of Satisfaction (COS), missing photos or moisture logs, invoicing batched to month end | 12 days |
| 4. Collection | Final invoice sent to payment in the bank | Accounts receivable (AR) | Carrier or adjuster review, a disputed line, a mortgage company endorsement, nobody following up | 25 days |
The example is the same ten jobs from above, and the legs add back up to it: 3 plus 31 is the 34-day production cycle, and 12 plus 25 is the 37-day gap. The split shows something the two totals hide. A third of that gap, 12 days, is closeout, and closeout is entirely inside your own four walls. No carrier, adjuster or accounts payable clerk is holding it. The example figures are illustrative, not a benchmark. Pull your own.
Then cut each leg by who owned it. Response by dispatcher, production by project manager, closeout by the project manager who closed the file, collection by payer. A company average of 12 days in closeout often turns out to be one person at 4 days and another at 25, and that calls for a coaching conversation with one person.