The fastest way to lose your money on a commercial job is to miss a deadline you did not know existed

A RocketLevel guide, backed by decades of experience in the trade. Commercial and public work gives you powerful tools to secure payment, mechanics liens and bond claims, but they only work if you protect them in advance, sometimes with a notice sent within days of starting. Miss the window and you forfeit the right.

<aside> βš–οΈ

Reviewed October 2026. Lien and bond-claim laws change, and they vary by state. Use this page to know what to ask, then confirm with your state agency or a construction attorney before you rely on it.

</aside>

Why this matters more on commercial

The mechanisms to know

Retainage: what your state lets the other side hold

Five to ten percent is the range you will be offered on a commercial contract, which is RocketLevel's working figure. Customary is not the same as permitted, and this is one of the few places in the payment chain where a number written into a signed contract can simply be unenforceable. Whether your state caps retainage, at what percentage, above what contract size, with what carve-outs, and on what release clock, is set by that state's statute. Three are set out below against the statute text (state rules as of October 2026). For anywhere else, pull your own state's statute, and check separately whether it requires retainage to step down at a completion milestone or to be held in a separate or interest-bearing account, because those are written state by state too.

California. Civil Code 8811 caps a retention withheld by an owner from the direct contractor at 5 percent of the payment, and provides that in no event shall the total retention proceeds withheld exceed 5 percent of the contract price. Read the date before you read the number. It reaches contracts entered into on or after January 1, 2026, so it does not touch a contract signed before that line, which is the part people miss on a job they are billing today. Two carve-outs. It does not apply on a residential project that is not mixed-use and does not exceed four stories. And it does not protect a subcontractor who was given written notice before the bid request that a performance and payment bond would be required and then failed to furnish one.

New York. General Business Law 756-c lets an owner retain no more than five per centum of the contract sum, holds a contractor or subcontractor to the same five percent and to no more than the percentage the owner itself retained, and requires release no later than thirty days after final approval of the work, with interest at one percent per month on anything held past that. A contract term demanding more is void under 757. Coverage is the half that gets quoted wrong. The article reaches a construction contract as General Business Law 756 defines it, meaning an aggregate project cost of $150,000 or more, and that definition excludes a one, two or three family residential dwelling, a residential tract development of one hundred or fewer one or two family dwellings, a project of four thousand five hundred square feet or less, and certain assisted residential projects under seventy-five units. Confirm you are inside the definition before you rely on the cap.

New Mexico. No retainage at all. Under NMSA 57-28-5(E), when making payments "an owner, contractor or subcontractor shall not retain, withhold, hold back or in any other manner not pay amounts owed for work performed."